Construction Timeline and Key Milestones
Oct 2023: Construction Starts
We began work in October, kicking off with a major phase of opening up and exploration. The properties had been unoccupied for over three years, and the neglect was evident in many areas. The roofs were leaking, the electrics were failing, and water wasn’t flowing—issues fundamental to a successful hospitality business. We wasted no time in getting started.
Q4 2023: Progress and Discoveries
The start of any project is always filled with excitement and the joy of discovery. As we opened up Quinn's and pulled back the shutters, we uncovered many hidden gems.
The early months kept us busy clearing rooms and repairing leaks. Every time it rained, we found another leak to fix. Gradually, we triumphed over the water damage. We also began clearing out the Boyle Sports fit-out, unveiling the amazing space we now fondly call Ray's Bar.
Revealing and clearing became the dominant themes of this quarter, enabling us to begin shaping the project’s vision.
Q1 2024: Key Works and Milestones
- Removed old partitions on the second floor of all buildings.
- Cleared overgrowth in the Food Yard.
- Stripped out the Boyle Sports fit-out, revealing stunning Victorian brick walls that will feature prominently in Ray's Bar.
- Removed the Boyle Sports shopfront, uncovering the original glazed tile finish.
- Stripped out old beer lines and began preparatory work for new lines to ensure consistently cold beer in the future.
- Tested sample paint colors in the original Quinn's Bar.
Q2 2024: Key Works and Milestones
- Cleared all rubble and remaining foliage from the Food Yard, unveiling its enormous potential to complement Quinn's.
- Reclaimed and recycled bar furniture, saving significantly on costs.
- Hauled away rotten timber and plaster, filling skip after skip.
- Fully resurfaced the yard with fresh hardcore—no more mud and dirt.
- Replaced the roof of Ray's Bar with new joists and timbers.
- Cleared the rear of Ray's Bar, making way for new toilets, an improved fire exit, and a rear staircase.
- Began sewage upgrades, partnering with Irish Water to install new pipes for all bathrooms, resolving longstanding issues.
- Replaced rotten roof and valley timbers, ensuring a dry pub.
- Revealed damaged bricks and granite sills after stripping the old shopfront from Quinn's, with plans to restore them.
- Completed a review of electrical wiring and appointed Lask for a full rewire of the properties.
- Started first-fix plumbing in all areas.
Q3 2024: Key Works and Milestones
- Excavated to extend and improve the old cold rooms. This five-month project raised the ceiling height, ensuring safer and more efficient access for staff while keeping beer consistently cold for patrons.
- Commenced significant electrical work, a key investment in the project’s future.
- Stripped out the old first-floor restaurant fit-out, uncovering original Victorian wallpaper.
- Recycled the old bar from Quinn's dance area to create a new bar for the restaurant.
- Removed external water tanks, creating a fully open space in the Food Yard.
- Stored reusable stone for future rebuilding.
- Progressed electrical work on the first and second floors.
Q4 2024: Key Works and Milestones
- Completed first-fix wiring on the first and second floors, paving the way to close up walls and floors.
- Installed a supersized gas main to power culinary talent in the Food Yard.
- Started first-fix wiring in Ray's Bar.
- Removed unused plant equipment from Quinn's rear, transforming the overgrown jungle into a manageable space.
- Nearing completion of the final dig in the main cellar—a challenging but rewarding task.
- Began installing a new 30,000-liter buried water tank, a crucial infrastructure upgrade.
- Installed the vintage Paddy Power mirror behind the bar on the first floor, adding a touch of character.
- Selected and paid a deposit for the new flooring in Ray's Bar: a stunning dark parquet floor from Wilsons Salvage Yard in Belfast.
- Final repair to all roof valleys
What’s going on at the moment?
We still have lot of work to do and below is list of the key work streams, and their current status (8th February 2025)
General Works
- Final pour of concrete in the main cellar - Completed in January
- Final install of the new cold rooms - Due for completion in Febraury
Rays Bar
- Install the flooring
- Install the new shop front and external signage. This new shop front is currently in design and will be ordered in February.
- Build the new bar - We have started this work in February
- Install the sanitary ware in the new toilets - This work in ongoing through February.
- Final fix on the electrical and lighting - This work in ongoing through February.
- Decoration
- Roof and external repairs - This work will be complete in February
Main Bar
- New flooring carpet - Selected and on order
- Final electrical works - This work in ongoing through February.
- Painting and Decoration - Ready to go but we have to wait for all the other construction work to be completed.
- Shopfront Restoration. brickwork and granite sills - This work is ongoing and will be complete in February.
- New External signage - This work is ongoing and will be complete in February
Rear Music Bar
- Complete wiring and sound system - Our electricians are onsite working on all wiring
- New flooring to repaired areas
- Build DJ Booth
- Decoration
1st Floor Restaurant
- New Kitchen - Commencing Febuary
- Complete new bar - This work has been completed
- Decoration - This work is ongoing
Upper Floors/Accommodation
- Install Carpets
- Install sanitary ware - This work is ongoing
- Decorating
- Furnishings - In Storage
Food Yard
- Noise barrier/side fence
- Shop front restoration and protection - This work will commence in February
- Steps and levelling
- Furnishings and Decoration
- Food Trucks install points.
- Canopies to all shop fronts - These are on order and will be installed in March.